The project of the Mayan Trainthe largest infrastructure project of the current federal administration, showed delays on some of its fronts within a few weeks to be inaugurated in its entirety.
According to the Sixth Government Report of President Andrés Manuel López Obrador, as of June 30 of this year, the further delays were in the Construction of seven booths and 10 visitor service centerswhich showed progress of 39.4 and 51.5 percent in work, respectively.
The report, sent to Congress on Sunday, added that the Construction of the six workshops and garages considered in the Maya Train project presented 55 percent progress at the end of the first half of the year.
As for the seven sections which make up the little more than 1,481 kilometers of route of the train, those that showed less progress They were the Stretch 4, from Izamal to Cancunwith 85.8 percent of the work; and the Stretch 5 South from Playa del Carmen to Tulumwith 87.7 percent completion.
In his message to the nation on Sunday morning, President López Obrador assured that In two weeks the Mayan Train will be fully inaugurateda work consisting of 34 stations along the route, which as of June 30 had an overall progress of 89.6 percent.
This project represents a new stage for the Mexican railway system and its purpose is to increase the economic impact of tourism in the region by avoiding the concentration of tourism in a single destination in the southeast. Sixth Government Report.
Maya Train: between expropriations and injunctions
To complete the Mayan Trainthe federal government has turned to the expropriation of private and social spacesin addition to facing various appeals.
“In order to continue with its construction, they have been published 122 decrees expropriating social property and 11 decrees expropriating private propertywhich correspond to 465 properties,” says the Sixth Government Report.
He also indicated that a total of 1,000 cases have been attended to. 52 amparo trials promoted by various actors in society such as interested individuals, civil associations and some residents of the areas through which the project will pass and who considered themselves affected by the construction work, the clearing and felling works, or the expropriation procedures.